Given the following project network where the times are in weeks and the costs in $:
Task Normal Time Crash Time Normal Cost Crash Cost IP
A 6 4 8000 14000 –
B 1 1 4000 4000 A
C 8 4 8000 24000 –
D 5 3 10000 24000 C
E 9 5 10000 18000 B,C
F 12 6 20000 36000 D,E
G 3 2 10000 18000 F
a. Determine the critical time.
b. Identify the critical path(s)
c. What is the minimum time that this project can be completed?
d. What is the total cost to achieve the answer in part c?
e. What is the optimal system crash time assuming there is a $10,000 per week penalty for
every 20 weeks?
f. What specific tasks are crashed and by how much?
g. What is the total system cost associated with the answer in part f?
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more