(3 points) 1.       the injection molding department of alvec inc.

(3 Points)

1.       The injection molding department of Alvec Inc. uses 40 pounds powder X a day. The plant operates 250 days per year. The daily usage of powder X is normally distributed with a standard deviation of 5 pounds per day. The lead time to obtain powder X from a supplier in 9 days. The annual holding cost is $2.00 per unit and the cost of ordering powder X is $50.

 

 

a)      What is Economic Order Quantity? ( 3 points)

 

 

 

2.       Refer to problem 1 and its solution. The injection molding department of Alvec Inc. uses 40 pounds powder X a day. The plant operates 250 days per year. The daily usage of powder X is normally distributed with a standard deviation of 5 pounds per day. The lead time to obtain powder X from a supplier in 9 days. The annual holding cost is $2.00 per unit and the cost of ordering powder X is $50.

 

 

a)      If a company has a service level goal is 99.4%. What is the expected pounds of shortage order cycle? (shortages are measured in terms of numbers of units) (2 points)

 

 

 

 

 

 

b)      Determine the order points for a service level of 99.4%. (4 Points)

 

 

 

 

 

 

 

3.       Draw the Activity-on-Arrow network diagrams for the following PERT problem. Use the minimum number of necessary “dummy” activities. (5 points)

 

Activity

Immediate Predecessor

A

B

C

A, B

D

B

E

C, D

 

 

 

 

 

 

 

 

 

 

 

4.       Given the demand of 3000 units and the following bill of materials for the item “A”, determine the low- level- code and the net requirements for all the items (A, B, C, D). (5 points)

 

Items

Current Inventory

Low- Level- Code

Net requirements

A

600

 

 

B

1800

 

 

C

20000

 

 

D

7200

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5.        (12 Points) The following information is gathered for a project.

 

Activity

Activity Time ( Days)

Immediate Predecessor(s)

A

2

B

4

A

C

5

A

D

2

B

E

1

B

F

8

B, C

G

3

D, E

H

5

F

I

4

F

J

7

G, H, I

 

 

 

a)      Draw the network diagram using the AON (Activity on Node) Convention. (2 points)

 

 

 

 

 

 

b)      Determine the critical path, the amount of slack for each activity and the total completion time of the project. (7 Points)

 

Activity

ES

EF

LS

LF

Slack

CP

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

       Critical Path:                                                                                                                      Project Completion time:

 

 

31

 

 

 

 

 

 

 

 

 

 

30

 

 

 

 

 

 

 

 

 

 

29

 

 

 

 

 

 

 

 

 

 

28

 

 

 

 

 

 

 

 

 

 

27

 

 

 

 

 

 

 

 

 

 

26

 

 

 

 

 

 

 

 

 

 

25

 

 

 

 

 

 

 

 

 

 

24

 

 

 

 

 

 

 

 

 

 

23

 

 

 

 

 

 

 

 

 

 

22

 

 

 

 

 

 

 

 

 

 

21

 

 

 

 

 

 

 

 

 

 

20

 

 

 

 

 

 

 

 

 

 

19

 

 

 

 

 

 

 

 

 

 

18

 

 

 

 

 

 

 

 

 

 

17

 

 

 

 

 

 

 

 

 

 

16

 

 

 

 

 

 

 

 

 

 

15

 

 

 

 

 

 

 

 

 

 

14

 

 

 

 

 

 

 

 

 

 

13

 

 

 

 

 

 

 

 

 

 

12

 

 

 

 

 

 

 

 

 

 

11

 

 

 

 

 

 

 

 

 

 

1 0

 

 

 

 

 

 

 

 

 

 

9

 

 

 

 

 

 

 

 

 

 

8

 

 

 

 

 

 

 

 

 

 

7

 

 

 

 

 

 

 

 

 

 

6

 

 

 

 

 

 

 

 

 

 

5

 

 

 

 

 

 

 

 

 

 

4

 

 

 

 

 

 

 

 

 

 

3

 

 

 

 

 

 

 

 

 

 

2

 

 

 

 

 

 

 

 

 

 

1

 

 

 

 

 

 

 

 

 

 

T A S K

A

B

C

D

E

F

G

H

I

J

C) Prepare the earliest start schedule (Gantt chart). (3 points)

 

 

 

 

 

 

Question 8

An aegean sea fish market buys swordfish daily for $2.10 per pound and sells it for $3.60 per pound. at the end of each business day any remaining swordfish is sold to a cat food company for $1.20 per pound. Daily demand can be approximated by a normal distribution with a mean of 150 pounds and a standard deviation of 9 pounds.

 

a) Determine the optimal stocking level for the Aegean sea fish market.

 

 

 

 

 

 

 

 

b) if the demand is distributed according to continuous uniform distribution with a mean of 150 pounds and the minimum and the maximum demand values are 130 and 170 pounds respectively, what is the optimal stocking level? Assume that all of the cost values remain the same.

 

 

 

 

 

 

Question 9

A radio manufacturer uses 60000 knobs per year for its popular car stereo series. The firm makes its own knobs, which it can produce at a rate of 600 per day. The radios are assembled uniformly over the entire year. The unit cost of an item is $8 and the carrying rate per year is 15% of the item cost. The setup cost for the production of knobs is $60. The firm operates 300 days per year. Determine each of the following.

 

a) optimal run size (production quantity)

 

 

b)minimum annual carrying cost (show work)

 

 

 

c) minimum annual setup cost (show work)

 

 

 

d) time of usage (cycle time)

 

 

 

e) time of production (run time)

 

Question 10

 

A manager has prepared a forecast of expected aggregate demand for the next six months. Develop an aggregate plan to meet this demand given this additional information:

A level regular time production rate of 100 units per month will be used. Backorders are allowed and they are charged at a rate of $5 per unit per month. Inventory holding costs are $3 per unit per month. Develop an aggregate plan to meet demand given the following additional information:

Current inventory is zero

Current employment level is 9 employees

Each employee can produce 10 units per month

Regular time production cost is $20 per unit up to 120 units per month

Inventory holding (carrying) cost is $3 per unit per month

Backorder (backlog) cost -$5 per unit per month

Employee hiring cost  – $20 per employee

Employee firing cost  – $10 per employee

Desired ending inventory -0 units

 

 

Month

Forecast

1

80

2

100

3

120

4

110

5

100

6

90

 

 

 

 

 

a) Level plan

month

1

2

3

4

5

6

Forecast

80

100

120

110

100

90

Output production(regular)

 

 

 

 

 

 

Beginning inventory

 

 

 

 

 

 

Ending inventory

 

 

 

 

 

 

Average inventory

 

 

 

 

 

 

Backlog

 

 

 

 

 

 

 

Costs

 

Inventory cost

 

Backlog cost

 

Production cost(regular)

 

Cost of Hiring / Firing

 

Total cost

 

 

 

 

 

 

 

 

 

Place your order
(550 words)

Approximate price: $22

Calculate the price of your order

550 words
We'll send you the first draft for approval by September 11, 2018 at 10:52 AM
Total price:
$26
The price is based on these factors:
Academic level
Number of pages
Urgency
Basic features
  • Free title page and bibliography
  • Unlimited revisions
  • Plagiarism-free guarantee
  • Money-back guarantee
  • 24/7 support
On-demand options
  • Writer’s samples
  • Part-by-part delivery
  • Overnight delivery
  • Copies of used sources
  • Expert Proofreading
Paper format
  • 275 words per page
  • 12 pt Arial/Times New Roman
  • Double line spacing
  • Any citation style (APA, MLA, Chicago/Turabian, Harvard)

Our guarantees

Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.

Money-back guarantee

You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.

Read more

Zero-plagiarism guarantee

Each paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.

Read more

Free-revision policy

Thanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.

Read more

Privacy policy

Your email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.

Read more

Fair-cooperation guarantee

By sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.

Read more