WEEK 4 CALEDONIA PRODUCTS PAPER
1. Why should Caledonia focus on project free cash flows as opposed to the accounting profits earned by the project when analyzing whether to undertake the project?
2. What are the incremental cash flows for the project in years 1 through 5 and how do these cash flows differ from accounting profits or earnings?
3. What is the project’s initial outlay?
4. Sketch out a cash flow diagram for this project
5. What is the project’s net present value?
6. What is its internal rate or return?
7. Should the project be accepted? Why or why not?
8. In capital budgeting, risk can be measured from three perspectives. What are those three measures of a project’s risk?
9. According to the CAPM, which measurement of a project’s risk is relevant? What complications does reality introduce into the CAPM view of risk, and what does that mean for our view of the relevant measure of a project’s risk?
10. Explain how simulation works. What is the value in using a simulation approach?
11. What is sensitivity analysis and what is its purpose?
FIN 370 WEEK 4 CALEDONIA PROJECT PAPER
FIN370 WEEK 4 CALEDONIA PROJECT PAPER
FIN/370 WEEK 4 CALEDONIA PROJECT PAPER
Re: Cash Flow Analysis and Capital Rationing
We are considering the introduction of a new product. Currently we are in the 34% tax bracket with a 15% discount rate. This project is expected to last five years and then, because this is somewhat of a fad project, it will be terminated. The following information describes the new project:
Cost of new plant and equipment: $ 7,900,000
Shipping and installation costs: $ 100,000
Unit sales:
Year Units Sold
1 70,000
2 120,000
3 140,000
4 80,000
5 60,000
Sales price per unit: $300/unit in years 1–4 and $260/unit in year 5.
Variable cost per unit: $180/unit
Annual fixed costs: $200,000 per year
Working capital requirements: There will be an initial working capital requirement of $100,000 just to get production started..
FIN 370 WEEK 4 Caledonia Project LEARNING TEAM ASSIGNMENT
U can also Purchase FIN 370 Week 5 Assignment, DQ’s and Final Quiz (***** Just Click On Below Link *****)
FIN 370 Week 5 DQ’s
http://www.homeworkmarket.com/content/fin-370-week-5-discussion-question-fin-370-week-5-dqs
FIN 370 Week 5 Team Assignment
FIN 370 Week 5 Final Exam Quiz
Delivering a high-quality product at a reasonable price is not enough anymore.
That’s why we have developed 5 beneficial guarantees that will make your experience with our service enjoyable, easy, and safe.
You have to be 100% sure of the quality of your product to give a money-back guarantee. This describes us perfectly. Make sure that this guarantee is totally transparent.
Read moreEach paper is composed from scratch, according to your instructions. It is then checked by our plagiarism-detection software. There is no gap where plagiarism could squeeze in.
Read moreThanks to our free revisions, there is no way for you to be unsatisfied. We will work on your paper until you are completely happy with the result.
Read moreYour email is safe, as we store it according to international data protection rules. Your bank details are secure, as we use only reliable payment systems.
Read moreBy sending us your money, you buy the service we provide. Check out our terms and conditions if you prefer business talks to be laid out in official language.
Read more